Skip to workspace
BAS Bridge
System explorer

Central plant

CH-01 Centrifugal chiller

Start request accepted
SEQUENCE CLOCK 0s

Chiller, water circuits, and heat rejection

CH-01 · WATER-COOLED CENTRIFUGALStart request accepted
Simulated teaching plant
Three independent circuits · select a point to inspect
Centrifugal chiller plant: Start request acceptedOriginal equipment cutaway with a centrifugal compressor and finned motor above two cylindrical shell-and-tube vessels. Blue chilled water serves a building coil. Amber condenser water circulates through a cooling tower. Water moves only with independent flow proof, rotors require running proof, and labeled points open their inspector.PLANT GRAPHIC / SELECT A POINT TO INSPECTCH-01 · EQUIPMENT + HYDRONIC CIRCUITSBUILDING RETURN← CHILLED SUPPLYWARM WATER TO TOWER →TOWER WATER TO CONDENSERBUILDING LOADAIR-HANDLING COILSCHW PUMP: motor proof is separate from hydraulic flow proof.CHW PUMPCW PUMP: motor proof is separate from hydraulic flow proof.CW PUMPVAPOR SUCTIONDISCHARGECENTRIFUGAL COMPRESSOR + MOTORCentrifugal compressor and motor: animation follows actual simulated running proof.CONDENSER / HEAT REJECTIONCH-01 · CONDENSERWATER IN TUBES · REFRIGERANT SURROUNDS TUBE BUNDLELOCAL METERING / EXPANSIONECONOMIZER DETAILS SIMPLIFIEDEVAPORATOR / BUILDING COOLINGCH-01 · EVAPORATORINSULATED SHELL · EVAPORATING REFRIGERANT BATHLocal oil system and independent oil readiness proof.LOCAL OIL SYSTEMCOOLING TOWERFAN · FILL · COLLECTION BASINPrimary leaving-water control measurement; an invalid value is not silently substituted.AILeaving chilled water50.5 °FBuilding return-water temperature in the fictional load/flow balance.AIEntering chilled water50.5 °FIndependent hydraulic proof required before and during compression.BIEvaporator flow proofNOT PROVENFictional load as a percentage of 500-ton nominal capacity.AVBuilding load request65 %Verified simulated compressor operation controls refrigerant-path and rotor animation.BICompressor running proofNOT PROVENIllustrative local capacity-control position; percent position is not percent cooling capacity.AIInlet guide vanes0 %Qualitative variable-speed response; not an OEM speed map or surge limit.AICompressor speed feedback0 %Water returning from the cooling tower to the condenser.AIEntering condenser water94 °FWater leaving the condenser toward the tower; includes rejected compressor input.AILeaving condenser water94 °FIndependent hydraulic proof on the heat-rejection circuit.BICondenser flow proofNOT PROVENLeaving chilled water minus saturated evaporating temperature in this example.AVEvaporator approachNot operatingLocal oil readiness, distinct from pump command.BILocal oil-system readyNOT PROVENIndependent fan-running confirmation controls fan animation.BITower fan running proofNOT PROVEN
Chilled water: building ↔ evaporatorCondenser water: chiller ↔ towerRefrigerant inside the chiller
Original centrifugal equipment cutaway. Water motion follows independent flow proof; rotating equipment follows running proof. Select a label or pump to inspect its signal. Shell internals and expansion arrangements are simplified for training. Motion illustrates operation; particle spacing and rotor speed are not calibrated measurements.

The teaching controller has accepted a request and is preparing separate water circuits.

Leaving chilled water50.5 °FTarget 44 °F · entering 50.5 °F
Cooling delivered0 tons65% load · 100% active capacity ceiling
Condenser approachNot operatingSaturated refrigerant minus leaving condenser water
Compressor input0 kWNo compressor running proof
Current service callCooling comes on for the conference

The plant has a valid cooling request. Trace each prerequisite before expecting compressor proof.

Alarms0Open training →
Model scope and assumptions

Interactive teaching plant · simulated values · accelerated sequence · no connection to operating equipment

A single 500-ton illustrative water-cooled centrifugal chiller with an oil-lubricated compressor, variable-speed capacity control, separate chilled-water and condenser-water pumps, and a cooling tower. Oil-free, multistage, economizer and purge arrangements vary by selected machine.

Run or advance the sequence to observe the requested stage. Changing the case retains your operator commands.

Sequence time is accelerated and illustrative; elapsed seconds are not OEM purge, restart, or safety timer settings.

Case briefCooling comes on for the conference

Fictional training call · Convention-center central plant

Customer report

“The event staff want confirmation that cooling is coming online before attendees arrive.”

You are observing a normal scheduled startup with the plant operator.

SERVICE EVIDENCE

Prove the boundary before changing parts.

  • Two separate water circuits must prove flow
  • Oil preparation follows water proof in this example
  • Capacity rises after the compressor starts

WORKING RULES

Keep supervisory control and equipment protection separate.

  • A BAS enable is a request; the chiller's local controller retains safety and sequence authority.
  • Keep command, motor proof, water-flow proof and thermal response as separate evidence.
  • Condenser approach = saturated condensing temperature − leaving condenser-water temperature. Evaporator approach here = leaving chilled water − saturated evaporating temperature.
  • Cooling tons = 500 × water flow (gpm) × chilled-water delta-T (°F) / 12,000 for the example's water assumptions; fluid properties and measurement quality matter.
  • Heat rejected by the condenser includes both evaporator cooling and compressor input. The model closes that illustrative heat balance.
  • Oil and purge points are design-dependent. An oil-free or positive-pressure machine requires a different integration design.
  • All timeline delays, capacity response and readings are teaching assumptions. Obtain the exact selected unit's points, sequence and operating envelope before field work.

MANUFACTURER RESEARCH

Read the actual equipment literature.