Control and verification
Typical HVAC sequence examples
Compare enabling conditions, stages of operation and independent feedback with the project’s approved sequence.
Illustrative operating sequences
| Equipment | What to trace |
|---|---|
| Occupied AHU | Schedule or override requests occupancy. With required permissives, request fan start. Verify independent proof within the expected interval. Enable normal loops and ventilation according to the approved sequence. |
| VAV terminal with reheat | Determine zone mode and active airflow target. The damper loop controls measured flow. At heating demand the sequence can enable reheat subject to minimum flow and configured limits. |
| Outdoor-air economizer | Verify available outdoor-air cooling, ventilation minimum and mixed-air limits. Compare damper command with blade position and mixed-air temperature at useful load. |
| Chilled-water plant | Demand initiates the plant. Required water paths and pumps establish flow. Chiller receives enable subject to local permissives and timing. Compare flow, compressor operation and water temperatures. |
| Heating-water plant | Demand selects lead equipment and active supply target. Prove the applicable water flow and local ready state. Observe heat delivery before adding capacity under the staging rules. |
Field example
At a cooling VAV, airflow is below its active setpoint, damper demand is high and the actuator is fully open. Inspect upstream static and restrictions before changing zone proportional gain.
Practice and related lessons
Technical references
- PNNL · Air-side economizer operation and maintenance
- PNNL · Variable air volume systems
- Trane · Dedicated outdoor air with sensible-cooling terminals
- Trane · How a heat pump reversing valve works
- Trane Commercial · Heat pump technology and defrost
- Trane · Condenser water system savings
- U.S. Department of Energy · Energy-efficient commercial boilers
- ASHRAE · Guideline 36-2018 addendum x, chilled-water plant control
- SPX Cooling Technologies · Cooling tower range and approach
- Trane · ASHRAE 62.1 ventilation design discussion
- Johnson Controls · Optimal start