Airside commissioning

Accept a newly installed air handler and its exhaust interlock. Compare the installed setup with the project documents, correct discrepancies and record each retest.

CX-01 / Rev A

Tenant fit-out · AHU-01 and EF-01

Each checkout starts from repeatable simulated conditions. Project settings, test evidence and open issues are saved on this device.

Passed
0
Failed
0
Unverified
6
Engineering drawing, point list and sequence

Airside control drawing

  1. AHU-01 supply fan proof
  2. DDC proof timer
  3. EF-01 run output
  4. Exhaust motor and duct

On AHU-01, the heating output drives the actuator motor. The linkage moves the valve stem. The discharge sensor is downstream of the coil.

Sequence of operations

EF-01 starts on the first scan at or after 15 seconds of continuous AHU-01 supply fan proof. Loss of proof removes the start on the next scan. A new start requires the entire delay again. Use a scan interval of 1–5 seconds.

Approved point list

PointFunctionBACnet address
AHU-01.DATSupply air temperature (SAT)Device 11001 / AI 21
AHU-01.HTG-VLVHeating valve commandDevice 11001 / AO 15
AHU-01.HTG-VLV-FBHeating actuator positionDevice 11001 / AI 16
AHU-01.SF-STSSupply fan motor proofDevice 11001 / BI 7
EF-01.EF-CMDExhaust fan requestDevice 15001 / BO 3
EF-01.EF-STSExhaust motor proofDevice 15001 / BI 4

Network checkout

The graphic must poll the AHU-01 discharge sensor’s commissioned device and object.

Unverified

Sensor verification

At the discharge port, the displayed value must agree with the reference probe within 1.0 °F. Compare the probe and graphic before adjusting the simulated input trim.

Unverified

Actuator calibration

Stroke the heating valve to both endpoints. Allow 75 simulated seconds and compare the motor feedback with the stem witness. Acceptance tolerance is ±3 percentage points.

Closed

Unverified

Open

Unverified

Functional performance

Run the installed exhaust logic through normal operation, interrupted proof and recovery. To correct the sequence, open the DDC editor, load the exhaust starter and save your wired diagram.

Open DDC editor
Unverified

Restoration and handoff

Current heating valve hold · Automatic. Test an actuator endpoint, then release the hold before closing the project.

Unverified

Commissioning report

The report includes the current disposition, acceptance criteria, measurements, test times and prior exceptions.

Preview report
BAS Bridge · Simulated commissioning report
Airside tenant fit-out | CX-01 / Rev A | AHU-01 + EF-01
Disposition: Open for correction or verification.
0 passed | 0 failed | 6 unverified
Heating valve operator hold: Released

Point-to-point network binding — UNVERIFIED
The graphic must poll the AHU-01 discharge sensor’s commissioned device and object.

Discharge sensor verification — UNVERIFIED
At the discharge port, the displayed value must agree with the reference probe within 1.0 °F.

Heating valve · closed endpoint — UNVERIFIED
With a 0% output, the motor and independent stem witness must both reach 0% within 3 percentage points.

Heating valve · open endpoint — UNVERIFIED
With a 100% output, the motor and independent stem witness must both reach 100% within 3 percentage points.

Exhaust functional performance — UNVERIFIED
Pass the start delay, interrupted proof, loss of proof, airflow and restart checks in sequence CX-01.

Return actuator to automatic control — UNVERIFIED
After an endpoint test, relinquish the operator command and verify automatic control.