Lesson · 16 min
VAV airflow and coordinated AHU resets
Connect terminal airflow demand to duct pressure and supply-air temperature without treating one zone as the whole building.
The AHU and terminal solve related problems
A VAV terminal regulates zone delivery while the central fan provides the duct conditions needed by the system. Trend zone temperature and target, airflow and target, damper position, and reheat status together. PNNL's VAV O&M guidance uses these relationships to check whether terminal response fits demand. Damper position by itself cannot establish that the intended airflow reaches the zone.
Pressure reset follows system demand
A fixed high duct-pressure target can leave many dampers heavily throttled at part load. A demand-responsive reset can reduce unnecessary fan work while maintaining service. PNNL's pressure guide compares pressure, target, and terminal positions. Mostly closed dampers or several open, starved terminals are investigation clues; the approved reset sequence determines the actual requests, timing, limits, and exceptions.
A single demanding zone needs its own investigation
One terminal can dominate pressure demand because of an actual load or a local airflow, sensor, balancing, or duct problem. Compare it with other zones and verify the cause before increasing pressure throughout the system. A fully open command plus low measured airflow narrows the investigation, but does not distinguish inaccurate airflow sensing from insufficient available pressure or a physical restriction.
Supply-air reset is a tradeoff
At suitable part load, a warmer supply-air target can reduce cooling and reheat. It can also require more airflow and fan energy; humidity and demanding zones can constrain the choice. PNNL's discharge-air guide explicitly describes this tradeoff. Examine supply temperature/target, terminal demand, reheat, fan behavior, and relevant humidity conditions together rather than assuming warmer air always saves energy.
Field exercise
Fictional exercise: which next step best follows from this VAV pattern?
Knowledge check
Answer all four questions. Pass the field exercise and at least three questions to complete this lesson.
Sources and scope
These original exercises draw on the sources below. For equipment settings and field actions, use the exact model, firmware, approved sequence and site procedure. Sources reviewed October 20, 2026.