Connect terminal airflow demand to duct pressure and supply-air temperature without treating one zone as the whole building.

The AHU and terminal solve related problems

A VAV terminal regulates zone delivery while the central fan provides the duct conditions needed by the system. Trend zone temperature and target, airflow and target, damper position, and reheat status together. PNNL's VAV O&M guidance uses these relationships to check whether terminal response fits demand. Damper position by itself cannot establish that the intended airflow reaches the zone.

Pressure reset follows system demand

A fixed high duct-pressure target can leave many dampers heavily throttled at part load. A demand-responsive reset can reduce unnecessary fan work while maintaining service. PNNL's pressure guide compares pressure, target, and terminal positions. Mostly closed dampers or several open, starved terminals are investigation clues; the approved reset sequence determines the actual requests, timing, limits, and exceptions.

A single demanding zone needs its own investigation

One terminal can dominate pressure demand because of an actual load or a local airflow, sensor, balancing, or duct problem. Compare it with other zones and verify the cause before increasing pressure throughout the system. A fully open command plus low measured airflow narrows the investigation, but does not distinguish inaccurate airflow sensing from insufficient available pressure or a physical restriction.

Supply-air reset is a tradeoff

At suitable part load, a warmer supply-air target can reduce cooling and reheat. It can also require more airflow and fan energy; humidity and demanding zones can constrain the choice. PNNL's discharge-air guide explicitly describes this tradeoff. Examine supply temperature/target, terminal demand, reheat, fan behavior, and relevant humidity conditions together rather than assuming warmer air always saves energy.

Field exercise

Fictional exercise: which next step best follows from this VAV pattern?

Nineteen of twenty zones are maintaining their targets.One terminal reports 100% damper command and airflow below its target.The airflow sensor and local duct path have not been checked.The system is already at its normal pressure target.
Select the best supported next step

Knowledge check

Answer all four questions. Pass the field exercise and at least three questions to complete this lesson.

1Many dampers are nearly closed while duct pressure stays high at part load. What should be investigated?
2Which bundle best evaluates a VAV terminal?
3Why might raising supply-air temperature increase fan energy?
4Does one fully open, low-airflow terminal prove that the whole system needs more pressure?