Level 5 · Control logic and sequence development

Trace Boolean logic, interlocks and permissives

19 minutes · Intermediate

Reading open · Practical open · Knowledge check open

What you’ll learn

  • Evaluate AND, OR and NOT in a start request.
  • Distinguish permission to start from confirmation of successful operation.
Before you start · 2 related lessons0 of 2 prerequisites demonstrated. You can open this lesson at any time.

Translate the sequence into a truth test

In the example, Enable = (Occupied OR TimedExtension) AND Ready AND NOT Trip. OR allows either request to qualify. AND requires every gate outside the parentheses to be true. NOT converts an active trip into a false run permission. Write each input in plain language with its true state defined. A point named SmokeNormal may be true in a healthy condition, while SmokeTrip is false under that same condition. Confusing the two reverses the decision.

Place proof after the action it observes

A allows a start attempt. An can withdraw permission while a unit operates. A input then reports the result after a configured starting interval. A sequence that requires fan airflow before issuing the first fan start can deadlock. A downstream heating function may legitimately require proven airflow. Retain the equipment’s independent protective chain. The exercises change virtual logic only.

Represent a sequence as a state machine

A state machine keeps track of which stage the equipment has reached. In a training air handler, Idle waits for an occupied request and all required permits. Starting issues a fan request and starts a proof timer. A timely proof allows Running and enables temperature control. A proof timeout enters Fault, removes the run request and records the failed transition. The approved reset conditions determine when another start is permitted. Test each transition and interrupt the sequence once during Starting to see whether stale elapsed time carries over.

Occupied or extended run, subject to interlocks
  1. Occupied OR extension
  2. AND drive ready
  3. AND NOT trip
  4. Request fan start
  5. Evaluate proof after startup

Normal operation

Example training conditions

  • For the fictional rule Run = Occupied AND Ready, both inputs true produce a start on the next scan. Dropping Ready makes the output false at the next evaluation.
  • Trace each input, the gate value and the actual output separately.

Worked service example

The tenant extension button is active but the evening fan never starts.

Recorded field evidence · training example

  • Occupied = false. Extension = true.
  • Ready = true. Trip = false.
  • Program evaluates Occupied AND (Extension OR Ready).

The programmed expression stays false whenever Occupied is false. Compare with the approved sequence and use test cases for occupancy alone, extension alone and an active trip. The actuator and fan wiring have yet to receive a valid start.

Field procedure

  1. Write the approved expression and label the normal polarity of each contact.
  2. Evaluate each subexpression with the observed inputs.
  3. Test each request source and every inhibit independently in the simulator, then verify a returned proof.

Hands-on exercise

Exercise the input combinations, including a single true request and one blocking condition. Predict the output before toggling the last input.

Boolean permissive circuit

(Occupied AND load request) AND NOT trip → Stop

Use AND to prove a start with both requests. Record it, then trip the safety with the requests still present and prove the output drops.

Unit 4 service call

The operator enabled the AHU. Should the fan have started yet?

Predict which transition is permitted and when its proof timer starts. Bring back the source, reading and time of your strongest observation.

Open case simulator

Knowledge check

Pass at 80%.

1. Two parallel permission paths feed an OR gate. A is false and B is true. The gate feeds an AND with Ready=false. What is the final command?
2. For (Occupied OR Extension) AND Ready AND NOT Trip, inputs are false, true, true and false respectively. What result follows?
3. An operator reports an intermittent permit that is always true when inspected later. Which test can reveal the sequence of events?
4. A latched start request remains true while a local safety drops out. In the documented sequence, safety must stop the fan immediately. Which output behavior is correct?
5. A fan’s own start condition requires the airflow switch to be proven while the fan is initially at rest. Which sequence change resolves the circular dependency in the training program?

Field takeaways

  • Document signal polarity and parentheses.
  • Use startup proof timing appropriate to the measured response.