Start with the layer and the evidence
A vendor name on a graphic does not identify the controller that operates the equipment. Trace the operator interface to its supervisor and field controller. Record the exact model, firmware, application version, point identity and approved sequence. Confirm the compatible service tool, license, access and a usable backup before planning an edit. A reachable BACnet point does not establish permission to change its application.
- Operator layer: review schedules, alarms, trends and permitted setpoints; verify who owns an active command.
- Supervisory layer: coordinate equipment, integration, naming and site-wide functions; retain the site configuration and point map.
- Equipment layer: execute the local sequence and I/O logic; establish which controller and application govern the output.
Trane and Carrier: interface versus programming
Choose the product-specific workflow rather than treating every controller from one manufacturer as equally programmable. Trane's TU guide separates TGP2 programs, controller configurations, backups and firmware. Carrier's training distinguishes graphical programming from commissioning and graphics work. The linked vendor resources describe these roles; the installed model and software determine what is available.
- Trane: Tracer SC+ coordinates the building system and Tracer Synchrony is its browser interface. Tracer TU for Programmable Controllers includes the graphical TGP2 editor. The UC800 is not TGP2-programmable; configuration and custom programming are different operations.
- Carrier: i-Vu provides the BAS interface. SNAP builds and simulates custom sequences with graphical microblocks; Field Assistant supports discovery, service and commissioning. Controls Expert is a contractor training/certification program, not the programming application.
Honeywell/Niagara: check version and security configuration
Niagara is an integration and application framework, not a fieldbus. Honeywell WEBs installations are one branded implementation; Workbench is used to engineer Niagara stations. Driver support, point licensing, hardware and the OEM's approved release must be checked for the actual installation. AX belongs in legacy recognition and migration planning: Tridium's published deprecation date was July 1, 2021.
- Installed-base examples include WEB-8000 and CIPer controllers; these names do not establish an appropriate supported version or license for another site.
- Use the applicable hardening guide to verify platform TLS, Foxs, HTTPS, certificates, roles and signed modules. Niagara supports encrypted services, but permitting non-TLS Fox still permits unencrypted connections.
- A security dashboard identifies configuration and certificate/module issues; it does not prove that equipment operation or the entire OT network is secure.
Metasys: SCT and CCT serve different work
Johnson Controls' System Configuration Tool (SCT) supports supervisory-system engineering and archive maintenance. Controller Configuration Tool (CCT) supports the logic of compatible field equipment controllers, including configuration, simulation and commissioning. A Metasys REST integration does not replace CCT for a field-controller sequence. Confirm the tool release and controller package before opening or transferring an application.
- Controller examples: CGM/CGE are general-purpose controllers and CVM/CVE are VAV controllers; FEC/FAC/VMA are earlier families. Protocol and security support vary by model.
- Before an authorized change: preserve the application and supervisory archive as applicable, simulate the proposed sequence, plan physical checkout and record how to restore the approved configuration.
Field exercise
Fictional training site: a Metasys AHU heats during a documented cooling-only test. Which workflow best fits the evidence?
Knowledge check
Answer all four questions. Pass the field exercise and at least three questions to complete this lesson.
Sources and scope
These original exercises draw on the sources below. For equipment settings and field actions, use the exact model, firmware, approved sequence and site procedure. Sources reviewed October 20, 2026.