Point checkout and functional commissioning checklists

Record the requirement, stimulus, expected observation, actual result and restoration for a reproducible test.

Minimum evidence for a checkout record

Minimum evidence for a checkout record
Test itemEvidence to retain
Point identificationAsset, drawing revision, field terminal or network object, point name, units and normal polarity.
Analog inputIndependent reference at its sampling location, raw input, configured endpoints, displayed value, acceptance criterion and tolerance.
Binary inputObserve both documented states through an approved stimulus. Record field state, controller state, timestamp and alarm behavior.
Actuator outputRecord the command, terminal signal, actual stem or shaft position, travel time and delivered flow or thermal response at more than one operating point.
Sequence and timingRecord initial mode, preconditions, simulated disturbance, permissive transitions, expected timer durations and measured response.
Alarms and returnVerify onset against threshold and delay, annunciation, acknowledgment and return to normal. Record how the original condition was restored.
Restoration and signoffRelease temporary commands at the correct priority, confirm automatic control and normal mode, record unresolved deficiencies and the result of any retest.

Field example

For a virtual 2–10 V actuator commanded to 50%, expect 6 V at the receiver for linear scaling. Record actual volts, timed shaft position and delivered response. A screenshot of the command alone cannot close this check.

Procedure

  1. Agree the acceptance criteria with the applicable project documents.
  2. Capture baseline conditions and authorize any physical field test through the site process.
  3. Run the test, document exceptions, restore normal control and repeat the failed portion after correction.