Original module 09 assessment

Commissioning

Prove the installed points, test a sequence under load and leave a record another technician can reproduce.

Module examination

Pass at 80%.

1. With 99% actuator feedback, which observation directly tests linkage integrity?
2. The project tolerance is ±0.5°F. A traceable reference reads 56.4°F and a displayed input reads 57.2°F. What is the signed display-minus-reference error?
3. AI-3 changes correctly but the graphic follows AI-4. What should you check first?
4. During a temperature oscillation the valve feedback sticks, then jumps despite smooth requests. What takes priority?
5. A 90-second full-stroke actuator moves uniformly from 20% to 80%. Estimate its travel time.
6. For a linear 4–20 mA, 0–2 in. w.c. transmitter, what should 16 mA indicate?
7. A 2–10 V actuator is commanded to 75% during checkout. Which combination is the best acceptance evidence?
8. If proof returns at t=12 then drops at t=19, when should a 30-second continuous-loss alarm first occur?